Energy Savings Performance Contracting  (ESPC)  Project Review
  Energy Conservation Savings Measure # Technical Category Project Title Installation Cost Energy Dollar Savings Other Savings Total Savings Simple Payback (Yrs)
Delivery Order #1 ECSM 1 Co-generation Plant Adsorption Chiller Operation  $           4,000  $       17,300  $            -    $     17,300 0.23
ECSM 2 Co-generation Plant Cogeneration Precooler  $       388,600  $       97,200  $    (20,400)  $     76,800 5.30
ECSM 3 Lighting Improvements Interior and Exterior Lighting  $    1,519,000  $     192,500  $       8,700  $   201,200 7.51
ECSM 4 HVAC System Improvements Mechanical System Improvements - Saunders Fine Arts Building  $         22,000  $         1,200  $            -    $      1,200 18.76
Delivery Order #2 ECSM 1 Electric Power System Improvements Distributed Generation  $    4,063,000  $     807,000  $            -    $   807,000 5.00
ECSM 2 Co-generation Plant Cogeneration System Optimization  $         57,800  $       25,000  $            -    $     25,000 2.30
ECSM 3 HVAC System Improvements Mechanical System Improvements - Boutwell Dramatic Arts/Tucker Theater  $    1,731,000  $              -    $            -    $           -   NA
ECSM 4 Miscellaneous Vending Miser  $         51,700  $         6,400  $            -    $      6,400 8.10
ECSM 5 Lighting Improvements Interior and Exterior Lighting (adjustment in savings calculation following DG installation)  $                -    $      (76,600)  $            -    $    (76,600) NA
Ending Numbers    $    7,837,100    $1,058,300 7.41

 


   Center for Energy Efficiency | MTSU Box 57 | Murfreesboro, TN 37132
Phone 615-904-8096 | Fax 615-904-8093 | e-mail
cee@mtsu.edu

MTSU is a Tennessee Board of Regents Institution. MTSU is an equal opportunity, non-racially identifiable, educational institution that does not discriminate against individuals with disabilities.